Miller Knight were appointed to carry out the remedial Passive Fire Protection works at the Bede Park student accommodation scheme in Leicester.
Service provided:
- Full on site setup including Resident Liaison Officer and Site Management team.
- The sealing of all unprotected service penetrations / voids within communal areas in the building.
- The recording of all works carried out using Firetronic software.
- Redecoration / resinstatement works.
- Ensuring minimal disruption as students were studying for their exams at the time of the work.
Client
Empiric Student Property
Scope of Works
Remedial passive fire protection , fire door upgrades, reinstatement works.
Contract Value
£260k
Duration
May 2021 - Aug 2021